bb01268bcba91d18746ba49bc7e235bc797da8bf
Full deadline tracking engine for Romanian construction permitting: - 16 deadline types across 5 categories (Avize, Completări, Analiză, Autorizare, Publicitate) - Working days vs calendar days with Romanian public holidays (Orthodox Easter via Meeus) - Backward deadlines (AC extension: 45 working days BEFORE expiry) - Chain deadlines (resolving one prompts adding the next) - Tacit approval auto-detection (overdue + applicable type) - Tabbed UI: Registru + Termene legale dashboard with stats/filters/table - Inline deadline cards in entry form with add/resolve/remove - Clock icon + count badge on registry table for entries with deadlines Also adds CLAUDE.md with full project context for AI assistant handoff. Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>